Water Improvement Projects
Project Updates
Major Water Storage Tank Projects
Tanks provide increased available water to the system for fire flow and during peak demand periods, while stabilizing water pressure to our customers. As the water system has continued to grow the Authority has planned investment into building new tanks to ensure that optimal water service is provided under all situations.
Main Replacement and Improvement Projects
In 2024, the Authority is continuing its aggressive Main Replacement Program. We work closely with local municipalities to coordinate and schedule additional main replacement projects as opportunities become available.
Areas of Active Projects
- Franconia Township
- Hatfield Borough
- Hatfield Township
- Hilltown Township
- Lansdale Borough
- Lower Salford Township
- New Britain Borough
- New Britain Township
- Sellersville Borough
- Skippack Township
- Souderton Borough
- Towamencin Township
- Worcester Township
No current projects.
Project: Broad Street, Hatfield 8” Water Main Replacement
Location: Broad Street between Main Street and Towamencin Avenue
Timeline: Beginning October 7, 2024 – duration approximately 7-8 weeks
No current projects.
No current projects.
Project: West Sixth Street, Lansdale, 8” Water Main Replacement
Location: West Sixth Street starting at Walnut Street and ending at the block end
Timeline: Beginning October 14, 2024 – duration approximately 4-5 weeks
No current projects.
No current projects.
No current projects.
No current projects.
No current projects.
No current projects.
No current projects.
Project Location Map
Developer Projects
Throughout our service area there are projects involving the extension of our water system into a new development. Typically, this work is done by the Developer’s own contractors; however, NPWA provides oversight to ensure that the work is completed according to required standards and specifications. We always analyze each extension of our system to determine if there is the potential for any adverse impact on our existing customers. NPWA works with developers to ensure that all extensions are done in a way to minimize any impact to our valued customers.
Road Improvement Projects
The NPWA service area has been impacted by several PennDOT road improvement and bridge replacement projects. The Authority has been closely involved in coordinating construction efforts. Road improvement projects require NPWA’s involvement to ensure the water facilities are maintained and protected as the roadway is excavated and reconstructed. In some cases, PennDOT projects require relocation of facilities that are in conflict with the construction improvements. In other cases, NPWA considers potential extension or replacement of main prior to completion of final roadway paving. This prevents reopening a newly paved roadway as well as serves as a cost savings for water main improvement projects.
Project Media
Sitemap
Contact Info
Copyright © 2024 North Penn Water Authority • Site: BCG • Privacy Policy